IT’S NOT A BRIDGE TO NOWHERE.
“What has happended to the progress (or lack thereof) on the bike/walk bridge connecting West and North Natomas?”
-Gregory G.

Councilwoman Angelique Ashby’s office helped us get an answer from Zuhair Amawi in the city’s Department of Transportation about stalled construction on the pedestrian/bicycle bridge over Interstate 80, which started in June 2010.
According to Amawi, work on the project is scheduled to resume May 1 and the bridge completed by September 2011. Construction stopped temporarily – a winterization period – in compliance with the environmental guidelines set forth by the U.S. Fish and Wildlife Service for the Giant Garter Snake habitat in the area.