“Is there a way to find out what other Natomas parks will be getting shade structures? As the parent of a toddler, I’m really excited about the prospect. I think shade structures over playground equipment are long over due.”
-reader via e-mail
Sarah Novo, Director of Constituent Affairs for Councilwoman Angelique Ashby answers:
- Burberry Park (2) – Construction began June 15 and is currently 75% complete. Construction is expected to be complete by August 12. Delays due to missing bolts.
- Tanzanite Park (1) – Construction began June 15. Construction is currently 25% complete, and expected to be complete by August 12.
- Kokomo Park (2) – Construction began July 28. Construction completion expected by beginning of September.
- Redbud Park (1) – Construction expected to begin by the end of August. Construction expected to be complete by year-end 2011.
- North Natomas Park (2) – Construction to begin in October. Project expected to be complete by year end 2011.
- Westlake Park (2) – Construction to begin in October. Project expected to be complete by year end 2011.
- Quail Park (1) – Construction to begin in October. Project expected to be complete by year end 2011.
- Riverview Park (1) – Construction expected to begin by November. Project expected to be complete by year end 2011.
- Autumn Meadow Park (1) – Construction expected to begin by December. Project expected to be complete by year end 2011.